Go to menu Project -> Maintain Baselines. In Earned Value tab, select “At completion values with current dates” Go to the menu Admin -> Admin Preferences. ![]() ![]() In this case, first, you have to make an important configuration. Option 1: Creating a new baseline based on the current schedule and assign the new baseline to the project. There are some ways to update the baseline in Primavera P6. In this post, I will show you how to update the baseline schedule in Primavera P6.Ĭonsider a simple project, which has a baseline assigned as illustrated below:Īfter several update periods, the project is delayed quite far from the baseline.Īfter discussion with the Owner, they authorized us to rebaseline the schedule and update our baseline to be identical to the current schedule. ![]() However, in some cases, schedule rebaselining might be required. The baseline Schedule is something we usually do not change.